The Federal Govt Council (FEC) has accredited tasks to shore up energy provide throughout the nation.
Minister of Energy, Abubakar Aliyu, briefed State Home correspondents after the Federal Govt Council (FEC) assembly presided over by Vice President Yemi Osinbajo on Wednesday on the Presidential Villa, Abuja.
Aliyu mentioned that the tasks have been aimed toward strengthening the capability of the Transmission Firm of Nigeria(TCN) and shoring up the facility provide within the nation.
“I introduced two memos to council at present which council has accredited; the primary memo council accredited the award of contract for design provide and set up of 1x60MBA, 132×33 KV transmission substation with related 4×132 KV line bay extension at Hong native authorities and Adamawa within the sum of N6.5 billion consisting of two elements one is offshore and onshore.
“ The offshore is 6.9 million {dollars} and the onshore is N3.3 billion on the CBN prevailing trade price and seven.5 per cent VAT; the supply interval is 24 months.
“This seeks to lift the capability of the provision round that space and it’s going to have an effect on so many cities and villages, there’s a vital native authorities headquarters round that space.
“It’ll have an effect on Track which is an area authorities headquarters in Adamawa state; Gombi can also be one other native authorities headquarters; Garkida city after which Hong.
“Then Mudi, Woba, Michika, Madagari. There may be an current 132 that passes by this space; so, what we’re doing now could be to drop a substation there.
“The hope is by the point all these interventions we’re making on the grid, reaches as much as 11,000 or there about that will probably be capable of stand up to and take it off; so, that is the intervention.’’
The minister mentioned that the second memo additionally was to acquire energy transformers and related spare elements for TCN to be deployed to 6 areas.
“One is to Aiyede in Oyo; Offshore part 1.8 billion {dollars}, the onshore is N98 million.
`The second is Gusau in Zamfara; the third one is Kankia in Katsina state; the following one is Minna, Niger; then the fifth one is to Okearo in Ogun.
“The sixth one is in Damaturu, Yobe; this one may be very peculiar as a result of as chances are you’ll remember, for over one yr, Maiduguri has not been having fun with full electrical energy.
“We have been capable of take electrical energy provide by an outdated line of 33 KV which we repaired and restored and have been capable of take 10 megawatts to Maiduguri over 130 kilometres on a 33 single circuit.
“We restored that round three to 4 months or thereabout; so they’re having fun with however little or no; by the point the electrical energy reaches Maiduguri, it’s going to drop to 6 or seven megawatts due to losses alongside the way in which.’’
Aliyu mentioned that the 330 takes energy to Maiduguri was vandalised by insurgents.
He mentioned that the ministry tried various instances to revive it however the insurgents would return and pull down the towers.
“So, we now determined, in the principle time to take the electrical energy by the 33 KVA which they’re having fun with however not as they might prefer it to be. It’s being rationed across the time.
“So, we’re presently procuring one other 33 double circuits new one to Maiduguri alongside the identical route.
“So the thought is that if somebody tampers with it, it’s straightforward to revive it inside a day or two, in contrast to the larger one which is the 330 which takes weeks or months to revive as a result of it’s within the bush.
“So, as it’s now even the one which we’ve put in, we’ve been doing cover and search, typically they are going to pull one-two poles, we are going to restore and for this reason we’re doing this endeavour by the roadside; it’s this to maintain on restoring again.’’
He mentioned that, at current, the contractor has returned to revive the principle line, 330 that was vandalised a while again.
The minister mentioned that, with the intention to have sufficient electrical energy for Damaturu and environs, from that substation Damaturu, and take some to Maiduguri, the venture would increase the capability of the Damaturu substation.
“So, the sixth one is at the price of 6.7 million {dollars} whereas the native part is N1.3 billion for the Damaturu improve injection transformer.
“So, the whole accredited for these is the greenback part is 22. 6 million {dollars} and the naira part is N5.1 billion and the council graciously accredited the 2 memos,’’ he mentioned.