- Lagos to collaborate with the Federal Ministry of Works and Housing, Ogun state and FRSC on site visitors administration to ease site visitors on the Lagos-Ibadan Categorical.
- The Federal Controller of Works in Lagos mentioned the OPIC part will likely be open to site visitors on Monday whereas the Berger axis too will likely be accomplished by the top of the month of April.
- Rehabilitation works on the Apongbon part of the Eko Bridge that was broken by hearth will likely be accomplished and open to site visitors on Might 31, 2023.
The Lagos State Authorities has as soon as once more moved to enhance the site visitors scenario on the OPIC, Kara and Berger axis of the Lagos-Ibadan Expressway because the contractors pace up work on the challenge.
That is because the state authorities has reiterated its dedication to fixed session with the Federal Ministry of Works and Housing on Visitors Administration of the development hall of the expressway even because the work is ramping as much as completion.
This was made recognized in a press release issued by the Lagos State Commissioner for transportation, DR Frederic Oladeinde, on April 15, 2023, the place he assured the motoring public of expediting motion by the Federal Authorities on the completion of the challenge in document time as introduced by the Federal Ministry of Works and Housing.
Oladeinde, who was on obligation tour of the development zones particularly round OPIC, Kara and Beger axis, on the weekend, assured the motoring public that he’ll proceed to carry strategic conferences with the Federal Ministry of Works and its challenge Engineers to evaluate the mode of works and proffer options that may ease the pressure of site visitors impression confronted by highway customers.
Lagos collaborating with Ogun state, FRSC
The commissioner said that the Lagos State Visitors Administration Authority, (LASTMA), and its Ogun State counterpart, TRACE are working in collaboration with the Federal Street Security Fee, (FRSC) to ease the gridlock on the hall.
He expressed sympathy for the plight being skilled by motorists on the hall and appealed for calm as the development works will quickly come to an finish.
Talking on updates on the development works, the Federal Controller of Works in Lagos State, Engr. Umar Bakare defined that the three current lanes which the contractor normally labored with needed to be diminished to 2 at every of the development sections, thereby leading to site visitors buildup. He assured that the FRSC, LASTMA, and TRACE are normally on website to regulate site visitors.
He mentioned the contractor is rounding up work round Opic and with the completion of the Asphalt works, the part will likely be open to site visitors by Monday whereas the Berger axis too will likely be accomplished by the top of the month of April.
The Controller of Works additional defined that the contractor has elevated the variety of working gangs to 4 so as to enhance the spate of labor in direction of assembly up with the deadline of April.
Eko Bridge will open to site visitors by Might 31
Almost about Eko Bridge, Engr. Bakare said that the rehabilitation works of the bridge are ongoing, particularly on the fire-damaged part of Apongbon.
He added that work is being targeting the restoration of the structural defect brought on by the inferno and as soon as that is accomplished, he revealed that the bridge will likely be opened to site visitors by Might 31, 2023, whereas work will proceed on the opposite sections of the rehabilitated bridge.
He sought the cooperation of the Motoring public when it comes to compliance with site visitors guidelines and laws which is able to additional enhance motion across the development zones.
For the document
- The Federal Authorities had earlier mentioned that the Lagos-Ibadan expressway will likely be accomplished by the top of April, a improvement that will likely be an enormous aid to motorists and commuters.
- The Lagos State Authorities had in March assured motorists that its collaboration with the Federal Authorities will ease the site visitors scenario on Kara, Berger-OPIC axis alongside the Lagos-Ibadan Expressway.
- It defined that the evaluate of the site visitors administration plan turned essential in view of the sluggish motion of site visitors within the space.
- Recall that a couple of week in the past, the Federal Authorities mentioned that every one crash obstacles round OPIC on the Ibadan-bound carriageway on the Lagos-Ibadan expressway had been eliminated and the realm opened as much as allow the free circulation of site visitors, particularly throughout the Easter holidays.