BAKU, Azerbaijan, June 5. Solar energy crops in
Azerbaijan’s Neftchala and Bilasuvar are anticipated to be
commissioned in 2026, whereas building of the Absheron-Garadagh
wind energy plant will take three years, Murad Sadikhov, Director of
Masdar Azerbaijan stated in an unique interview with Pattern.
Sadikhov emphasised that these tasks are a part of UAE-based
Masdar’s mega-project initiative.
“On June 4, 2022, in Shusha, we signed two implementation
agreements with the Ministry of Power of Azerbaijan. As a part of
these tasks, we deliberate to construct and fee energy crops
with a capability of 1 gigawatt of photo voltaic and 1 gigawatt of wind
vitality within the first and second phases every.
On June 4, a groundbreaking ceremony was held for the 1-gigawatt
undertaking as a part of the primary part. These tasks embody the 240
MW Absheron-Garadagh wind energy plant (positioned on the Baku-Shamakhi
freeway, within the territory of Absheron and Garadagh), a 315 MW photo voltaic
energy plant within the Banke settlement of Neftchala area, and a 445
MW solar energy plant in Bilasuvar. Development of the solar energy
crops will probably be accomplished in roughly two years, with full
operation anticipated within the second quarter of 2026. The wind energy
plant’s building and commissioning will take about three years.
These are preliminary calculations, and a extra exact schedule
will probably be offered later because the tasks develop,” he defined.
On June 4, President of the Republic of Azerbaijan Ilham Aliyev
and UAE Minister of Trade and Superior Know-how Sultan bin
Ahmed Al Jaber laid basis stones for Neftchala, Bilasuvar
solar energy crops and Absheron-Garadagh wind energy plant.
The ceremony passed off on the opening of the twenty ninth Worldwide
Caspian Oil & Fuel Exhibition – Caspian Oil & Fuel and the twelfth
Caspian Worldwide Energy and Inexperienced Power Exhibition – Caspian
Energy as a part of the Baku Power Week on the Baku Expo Middle.
Annex to Funding Settlement, Power Buy Settlement,
Settlement on Connection to Transmission Community and Land Lease
Settlement on tasks of 445 MW Bilasuvar SPP, 315 MW Neftchala SPP
and 240 MW Absheron-Garadagh WPP have been signed between the Ministry
of Power and Azerenergy OJSC and Masdar of the United Arab
Emirates on June 4 in Baku.